This section of the website describes
everything that you need to know about Fosse
installations.
HISTORY and
BACKGROUND
Historically the French separated the grey
water (eau usee ) from showers, sinks, washing machine etc and
the sewage from the WC (eau vanne).
The eau usee was taken anywhere convenient
such as into the ditch alongside the road or even into a local
stream.
The eau vanne was either:
- piped into a fosse septique with an outlet
to a rudimenary filter bed that normally consisted of a
trench filled with stone (tranchee d'epandage)
- or piped into a fosse d'etanche that was
supposed to be emptied regularly.
The invention of the septic tank is attributed
to a French man named Jean-Louis Mouras who built the first
septic tank in Vesoul in 1860 and the first use of a septic
tank in France dates back to 1881.
The fosse septiques (septic tank) were often
very small but the fosse d'etanche can be 4 cubic metres or
more. Fosse d'etanches were often tampered with to reduce
emptying costs - by simply knocking a hole in the bottom - but
this only worked in areas where the limestone rock or gravel
prevailed and the water could drain down and pollute the same
acquifer that was being used for drinking water. It also often
backfired because in non-draining soils the tanks will often
fill up with rainwater and require even more frequent
emptying. Many people wonder why their tanks need to be
emptied more in the winter and cannot understand why they "use
more water in the winter than in summer".
Once in the tank the waste starts to divide
itself - the lightest parts of the waste (fat, oil, grease)
starts to float to the surface where they form a crust called
Suspended Solids. These will be digested by aerobic bacteria
and transformed into carbon dioxide and water. (Aerobic
bacteria : a micro-organism that requires oxygen to
live).
The heavier solids will drop and settle at the
bottom of the tank. This is called the sludge. They will be
digested by anaerobic bacteria. (Anaerobic: opposite of
aerobic) and the liquid will circulate in between the two
masses.
The septic tank does not really treat
waste. Its main purpose is to store the waste for a period
during which the waste will undergo its first transformation
called the pre-treatment. This "pretreatment" only removes
about 30% of the pollutants and the remaining 70% contains
germs and pathogens (such as hepatitis, polio, cholera, para
typhoid etc) which pose real threats of life threatening
disease.
The remaining 70% is purifed by the filter bed
that is now required for every installation - this is the
"treatment" that just does not exist in most existing
installations. It has been estimated that about 3 out of 4
French rural properties do not comply.
European law has forced the French government
to act - and not before time!
SEPTIC TANKS AND MAINS DRAINAGE
CONNECTIONS
The new regulations on the
installation of fosse toutes eaux are tough and now in place.
On the 3rd of January 1992, all towns and villages in France
saw their responsibilities increased and the Maire is now
responsible for every aspect of wastewater treatment, be it
collective or individual and is directly responsible for the
control and regular maintenance of your septic
tank.
The new laws impose an
obligation on each commune to prepare a map - called "Carte
d'aptitude des sols" that designates the area that should have
systems "collectif" or "non-collectif" . In the areas where
non-collectif systems (fosse toutes eaux) are designated each
commune has to have a pollution monitoring system in place by
the end of 2005 that will control the disposal of all
sewage.
Because most of the Maires are not specialists
in the field of wastewater treatment, they have in many cases
appointed a syndicate or a professional body to enforce the
law. They are often (but not always) known as S.P.A.N.C.
(Service Public d’Assainissement Non Collectif) and will
service a group of communes from a local office.
The responsible regional body is "Les
Directions Regionale et Departmentales des Affairs Sanitaires
et Sociales (DRASS) de your region." Each department in
each region will also have a "Les Directions Departmentale et
Departmentales des Affairs Sanitaires et Sociales (DDASS) de
your department" These offices will monitor and
administer the implementation of the new laws by the mairies
of each commune.
The law is all about pollution control
and does not impose any construction obligation on communes
that have designated "collectif" systems. So if a commune does
not have the money for a system "collectif" then do not buy a
house in the designated area because you will probably not get
consent for a "non-collectif" fosse toutes eaux.
If your property is in a designated
"collectif" area, where the main drains have been installed
you will eventually be obliged to stop using your existing
fosse septique and connect to the mains drainage in the
road.
Many of you will have noticed that your water
bill contains a line called “Redevance Service Public
d’Assainissement Non Collectif”. This is a charge applied by
your water company to help finance the implementation of the
law. The cost does vary depending on where you
live.
The main purpose of the control is to ensure
that all the systems which are not, or which cannot be, linked
to the main sewage system are in good condition, function
properly and are capable of dealing with the amount of
wastewater to be treated.
A visit to your property will be arranged by
SPANC and during the visit the technician will verify the
:
- Location of the tank
- Access to and condition of the tank
- Ventilation of the tank
- Volume of the tank
- Sludge level
- Drain going to the filtration system
- Nature of the soil
- Proximity of any water sources, above and
underground
- Filtration system
You will then receive a report that will
indicate whether or not your system is working correctly and
that will explain to you how to proceed with any required
changes.
REQUIREMENT FOR
DOCUMENTATION
All recent installations should have been
documented and the records placed with the Mairie.
If you are purchasing an old house in the
country ask to see the legal certificate of approved drainage
- It is unlikely that there is one and it will be the
responsibility of the new owner to get it. The notary will
need it before you can resell the property in the
future.
A visit to the Mairie is probably all that
will be necessary to decide whether or not a new fosse toutes
eaux or mains drainage connection is required. Bluepools can
undertake the application on behalf of the client where
required
APPLICATION FOR A NEW FOSSE
TOUTES EAUX
This is known as the "Demande d'installation
d'un dispoitif d'assainissement non collectif"
The application requires:
The application form completed and signed -
including number of main rooms, slope of the land, the ground
water level and the type and size of filter. A location
plan (1:25,000 or 1:10,000) A layout plan showing existing
and future buildings, the proposed location of the fosse
installation, any wells or streams and the slope and direction
of slope of the land.
COSTS OF FOSSE TOUTES
EAUX
The costs of Fosse toutes eaux installations
depends on the number of main rooms - because this directly
affects the size of the fosse elements.
The cost of concrete tanks can vary between
400 and 800 euros depending on the size and the builders
discount from the merchants.
The cost of polymer tanks will probably lie in
the same range even though the published price lists of many
major suppliers such as Frans Bonhomme indicate much higher
prices. The polymer tanks do need sand backfill around them
and need more careful installation.
The pipework and fittings between the house
and the filter bed will also cost several hundred euros.
Additional drainage runs can add a day to the programme and
increase the cost by up to 1000 euros.
The cost of the filter bed materials bed will
be approximately 30 euros per square metre.
A straightforward installation for a 5 main
room residence will take about 4 days - this could increase to
7 for a large complex installation. A team of builders with
their plant and equipment will cost about 750 euros per
day.
Hence total costs are likely to be as in the
following table. The cost of carting the excavation arisings
off site can increase the cost by 500 euros or more depending
on the filter size and the haulage distance to the local tip
(dechetterie).
|
Number of
main rooms (No of bedrooms + 2) |
Fosse toutes eaux costs in
euros |
|
less than
or equal to 5 |
5000 |
|
6 |
6000 |
|
7 |
7000 |
|
Each extra
room on top |
1000 |
The conclusion to be drawn is - do not
overestimate the number of rooms and never build a fosse now
for a future dwelling
Costs can be more for several reasons
including:
- The length of pipe runs
- The requirement for a pumping chamber(s)
- The number of drain connections from the
property
- The difficulty of installing the vent stack
above the roof
- The builders travelling / accommodation
costs
MAINS DRAINAGE
CONNECTIONS
If mains drainage has been or is about to be
installed then the house-owner will have been asked where they
would prefer the connection point to be located. When this
request is not answered the communes drainage contractor will
make the decision and mark the connection point on a plan.This
will be available for reference in the future and the
connection location will be required before your installation
contractor will be able to provide a fixed quotation.
The mains drainage connection needs to be
planned before the installation of a pool because it is
surprising how often the best locations for both result in a
clash. Hence the pool and main drainage connections need to be
just as carefully planned as a pool and fosse toutes eaux
installations.
The mains drainage connections will cause
quite severe damage to an established garden (As fosses also
do) and so it is preferable to install pool and these
connections at the same time both to reduce cost and some of
the disruption.
MAINS DRAINAGE CONNECTIONS
COSTS.
These can vary more than fosse toutes eaux
costs because the number of manholes and length / depth of
drain runs will vary significantly from project to project.
However in broad terms most mains drainage connections should
be a bit less than the cost of a fosse
installation.
MAINTENANCE OF FOSSE
SYSTEMS
The law requires that the fosse toutes eaux in
emptied at 4 year intervals or less. It is essential that the
property owner retains the invoice (facture) from the licensed
fosse evacuation contractor as the Mairie will ask to see this
during any inspection in the future.
When a fosse has been emptied it should be
refilled with fresh water and treated with a packet of EPARCYL
(can be bought in most supermarkets). This also applies to old
septic tanks after they have been emptied. A fosse that has
stopped working for any reason can also be kickstarted by
emptying, refilling and treating with EPARCYL.
TROUBLESHOOTING
| Smells in the
house |
- No water seal in toilets and
traps
- Evaporation of water seals
- Lack of high level ventilation
|
| Smells outside the
house |
- Fosse vent pipes <100 mm
- Fosse vent pipe blocked or not
carried above the roof
- Lack of extractor on top of
vent
- Lack of primary vent on the WC
pipe
- Fosse vent pipe not installed
properly
- Manholes on fosse out of
position
|
| Corrosion of the
steel reinforcement in the fosse |
- Lack of fosse ventilation
|
| Blockages in
internal drains |
- Grease
- Insufficient falls on pipework
- Pipe diameters too small
|
| Fosse
full |
- Fosse needs emptying
- Fosse to small for loading
|
| Foreign materials
in the entry manhole to the filter bed |
- Fosse needs emptying
- Fosse is too small
- Rainwater getting into the fosse
network
- Prefilter in fosse needs to be
changed
|
| Blockage of the
final manhole in the filter |
|
FOSSE TOUTES EAUX
TECHNICAL DETAILS
The installation will always
consist of two main systems:
- The pretreatment chamber (the fosse toutes
eaux ) - a concrete or polymer type tank
- The treatment element that is best suited
to the characteritics of the site - the filter bed.
Occasionally a grease trap (bac degraisseur of
500 litres) may be required but this should not be necessary
in non commercial premises and should be avoided if possible
because it is just something else to maintain or go wrong. If
it is not possible to keep the distance between the kitchen
and the fosse down to 10 metres or less a grease trap is
advisable and will probably be a technical requirement of the
consent documentation.
When an existing fosse system is being
replaced it must be cut out of the pipework system
entirely. It can be sealed up and left full of water - any
odour from it should reduce to nothing within a few days.
Alternatively, depending on its location, it may be preferable
to have it pumped dry and filled with sand.
FOSSE TOUTES EAUX
The volume of the fosse toutes eaux can be
determined from the following table:
|
Number of main rooms
(No of bedrooms + 2 |
Fosse toutes eaux
volume in cubic metres |
|
less than or equal to
5 |
3 |
|
6 |
4 |
|
7 |
5 |
|
Each extra
room |
+
1 |
The tank sizes are shown in the following
table:
|
Number of main rooms |
4 |
5 |
6 |
7 |
|
Fosse toutes eaux capacity
(m3) |
3 |
3 |
4 |
5 |
|
Depth of tank |
1.35m |
1.35m |
1.72m |
1.85m |
|
Length of tank |
2.52m |
2.52m |
2.52m |
2.52m |
|
Width of tank |
1.19m |
1.19m |
1.19m |
1.40m |
|
Weight |
1600kg |
1600kg |
1950kg |
2050kg
|
VENTS
Two vents are always required and these are
the most important part of the installation if odours are to
be avoided. Both vents must be taken above the property
roof eaves levels
Primary vent - 100 mm and taken from the
downpipe from the WC straight up through the roof
Secondary vent - 100mm and taken from the top
of the fosse outlet pipe, back to the property and then up an
outside wall - can be taken through or outside the roof
tiling.
FILTER BED
The size and type of filter bed is a function
of the number of main rooms, permeability of the soil, the
maximum ground water levels and the slope of the land on which
it is to be built.
The size (and cost) can be determined from the
following table:
|
Soil
type |
Filter
type |
Length of trenches or
minimum surface area of sand
filter |
|
5 main rooms or
less |
Each extra
room |
| Permeable sand or silt with a
minimum thickness of 1 metre |
Land drain trenches
500 mm wide x 500 mm deep
filled with 10/40 mm gravel surrounding slotted pipes
|
45m |
15m |
| A thick layer of soil on
fissured permeable rock |
Vertical sand filter without
drainage
Slotted pipes in 200 mm
gravel over a 700 mm deep sand bed covered with a
minimum 200 mm topsoil |
25 m2 |
5m2 |
| Impermeable soil
such as clay or when there is a risk of contaminating an
underground water resource |
Vertical sand filter with
drainage
As filter without drainage but with a
system of slotted water collection pipes in a 200 mm
layer of gravel below the sand filter. The water is then
piped or pumped to a suitable ditch |
25 m2 |
5 m2 |
| Land prone to
flooding or where the ground water is very near the
ground surface |
An above ground sand filter with sloping
sides
As vertical sand filter
without drainage but above ground |
Base area - 60 m2
Top area - 25 m2 |
Base area - 20 m2
Top area - 5
m2 |
Information
courtesy of Bluepools SARL |